Oficiali santrauka · English
Kas perkama?
Fingrid Oyj has decided to build new 2 x (400 kV + 110 kV) power lines between Toivila and Hikiä substations. The new transmission lines will be mostly located in the place of the existing 110 kV power lines. Both new transmission lines will be constructed with 400 kV + 110 kV structures. Only 400 kV conductors will be installed on the western transmission line (design code 2055). Both 400 kV and 110 kV conductors will be installed on the eastern transmission line (design codes 2084 and 2085). The length of part 3 (Ranttila-Hikiä) is approx. 46 km.
Informacinis mašininis vertimas. Oficialiai santraukai ir toliau teikiama pirmenybė.
Oficiali santrauka · English
Fingrid Oyj has decided to build new 2 x (400 kV + 110 kV) power lines between Toivila and Hikiä substations. The new transmission lines will be mostly located in the place of the existing 110 kV power lines. Both new transmission lines will be constructed with 400 kV + 110 kV structures. Only 400 kV conductors will be installed on the western transmission line (design code 2055). Both 400 kV and 110 kV conductors will be installed on the eastern transmission line (design codes 2084 and 2085). The length of part 3 (Ranttila-Hikiä) is approx. 46 km.
Nemokama
Gaukite kitus šio sektoriaus pirkimus
Kas savaitę gaukite el. laišką su naujais jūsų kriterijus atitinkančiais skelbimais. Prieš įjungdami nemokamus pranešimus patikrinkite arba pakeiskite kriterijus.
Skelbimo istorija
Pirkimo procedūros laiko juosta
Sekite pagrindinius šios pirkimo procedūros etapus ir atnaujinimus.
Kol kas nenustatyta jokių kitų susijusių skelbimų.
Duomenys pertvarkyti, kad būtų lengviau skaityti. Oficialus skelbimas ir pirkimo dokumentai visada turi pirmenybę.
Šaltinis ir patikimumas
TED · 446176-2026. Patikrinta 2026-08-23 09:05.
Duomenys pertvarkyti, kad būtų lengviau skaityti. Oficialus skelbimas ir pirkimo dokumentai visada turi pirmenybę.