Atribuit TED · Sursă · Limbă: English

Irlanda · Lucrări de construcții

Titlu oficial · English

EST Constr - Letterkenny University Hospital, Co. Donegal. Boiler House Upgrade

Health Service Executive (HSE) · Irlanda

Vezi anunțurile sub acest nume
Termen-limită Neanunțat
Valoare estimată4.434.405 EUR
Publicat1 sept. 2026
Deschideți anunțul oficial ↗

Rezumat oficial · English

Ce se achiziționează?

The project includes the Replacement of existing MTHW Boilers with 3 No. dual fuel MTHW Boilers. The contractor will be responsible for the installation of associated boiler plant including pressurisation equipment, Heat exchangers, circulating pumps, valves, pipework and insulation. A free standing flue installed adjacent the Boiler house will be adjusted for the new Boiler plant. The boiler house will be extensively renovated to accommodate the proposed new boiler plant and equipment. Builders works is required including construction and fitting out of the renovated boiler house, roof alterations to accommodate a new roof light and works associated with a Lpg tank compound. Electrical Works include replacement cabling, local isolators for boiler plant, emergency lighting and fire alarm w

Istoricul anunțului

Cronologia procedurii de achiziție

Urmăriți principalele etape și actualizări legate de această procedură de achiziție.

Nu a fost identificat încă niciun alt anunț asociat.

  1. Anunț privind rezultatul Anunțul curent

    · TED 600441-2026

    Deschideți anunțul oficial ↗

Datele sunt restructurate pentru o lectură mai ușoară. Anunțul oficial și documentele achiziției prevalează întotdeauna.

Sursă și fiabilitate

TED · 600441-2026. Verificat la 4 sept. 2026, 06:05.

Datele sunt restructurate pentru o lectură mai ușoară. Anunțul oficial și documentele achiziției prevalează întotdeauna.

Semnalați o eroare prin e-mail