The Contracting Authority wants to purchase the complete functional supply of a total of approximately 20 km 220 kV three-core submarine cable (installed as 3 separate, parallel cable systems) containing an optical fibre cable, including all labour, equipment and materials required for design, fabrication and factory testing, transport of cable and accessories to a port in Zealand, Denmark, installation of transition joints and hang offs and completion and commissioning as a part of a three new 220 kV cable system connecting Vordingborg Nord (VONØ) substation to Eskilstrup (ESK) and Nørre Radsted (NRA) substations. For further details concerning the purchase, reference is made to the tender documents.
Tradução automática indicativa. O resumo oficial continua a ser a referência.
Resumo oficial · English
The Contracting Authority wants to purchase the complete functional supply of a total of approximately 20 km 220 kV three-core submarine cable (installed as 3 separate, parallel cable systems) containing an optical fibre cable, including all labour, equipment and materials required for design, fabrication and factory testing, transport of cable and accessories to a port in Zealand, Denmark, installation of transition joints and hang offs and completion and commissioning as a part of a three new 220 kV cable system connecting Vordingborg Nord (VONØ) substation to Eskilstrup (ESK) and Nørre Radsted (NRA) substations. For further details concerning the purchase, reference is made to the tender documents.
Histórico do anúncio
Cronologia do procedimento de contratação pública
Acompanhe as principais etapas e atualizações associadas a este procedimento de contratação pública.
Ainda não foi identificado nenhum outro anúncio relacionado.
Os dados são reorganizados para facilitar a leitura. O anúncio oficial e os documentos do concurso prevalecem sempre.
Fonte e fiabilidade
TED · 655836-2026. Verificado em 23 de set de 2026 11:05.