What is being procured?
The contracting authority shall enter into a contract for a turnkey contract for the complete upgrading of the intermediate voltage installations at the Helldal and Loddefjord transformer stations. For this procurement, the contract will be signed in accordance with NS 8407:2011 General contract terms for turnkey contracts, with the changes and supplements included in chapter C2.