What is being procured?
LOT 1: Design and construction of WWTP for 50,000 PE, with secondary treatment and Ph removal. Works will be implemented following FIDIC conditions of contract ("Yellow Book", 1999 edition) LOT 2: -Rehabilitation/replacement/reconstruction of approx 33 km network -Construction of 4 pumping stations -Procurement of sewer water cleaning equipment Works will be implemented following FIDIC conditions of contract ("Red Book", 1999 edition)